Ethereum moves Glamsterdam’s Hoodi test to December 15, with no mainnet date set

Ethereum developers moved the Glamsterdam upgrade on the Hoodi test network from October 26 to December 15, 2026, but agreed to keep its proposed gas changes intact, according to Decrypt. The postponement followed an October warning from security firm ChainSecurity that the changes could weaken safeguards in existing smart contracts. Glamsterdam had already cleared the Sepolia test network, but developers had not set a mainnet activation date as of November 28.

December also brings a separate decision about Hegotá, the upgrade planned to follow Glamsterdam. An October 2026 update on ethereum.org listed the second quarter of 2027 as the mainnet target, with testing on Sepolia first. Neither date was confirmed, and developers were still debating whether to retain one of Hegotá’s two scheduled features.

Why Glamsterdam changes gas costs

Glamsterdam aims to give Ethereum more capacity without requiring node operators to use more powerful hardware. Its gas changes address database growth of about 120 GiB a year by making it more expensive to add accounts and contracts to the data that nodes must maintain. One proposal, EIP-8037, would raise the gas cost of creating an account to roughly seven times its current level. The upgrade would also change the cost of reading stored data. Not all operations would become more expensive: a standard ETH transfer between existing accounts could cost up to 71% less in gas.

Two other changes address how nodes receive and process blocks:

  • Enshrined proposer-builder separation (EIP-7732) would put the handoff between a block’s builder and its proposer directly into Ethereum’s protocol. That would remove the need for third-party relays and extend the time available to distribute block data from about two seconds to about nine.
  • Block-level access lists (EIP-7928) would tell nodes in advance which data each transaction will use. Nodes could then process transactions in parallel when their data does not overlap, and synchronize more quickly.

Other scheduled changes would let developers deploy contracts at the same address across chains, give applications a log for tracking ETH transfers and raise the maximum contract size from about 24 KiB to 64 KiB. Validator exits and consolidations would also become faster. When the fork reaches mainnet, node operators and stakers will need to update their clients; ordinary ETH holders do not need to take action.

Hegotá’s open question: transaction inclusion or quantum-resistance work?

Fork-choice Enforced Inclusion Lists, or FOCIL (EIP-7805), remained on Hegotá’s schedule as of November 28. Under the proposal, a committee of validators would identify transactions that block builders must include, limiting any single party’s ability to exclude a valid transaction. In November, some developers argued for dropping FOCIL to free up resources for work on quantum resistance. Developers were expected to decide Hegotá’s full scope in December 2026.

The other scheduled feature, Frame Transactions (EIP-8141), would let each account define what makes a transaction valid rather than rely on one fixed signature scheme. That would support social recovery, spending limits, multiple approvals and gas sponsorship within the protocol. It would also allow accounts to use signature schemes designed to resist quantum computers. Dozens of other proposals remained under consideration.

Ethereum completed four upgrades after the September 2022 Merge: Shanghai/Shapella in April 2023, Dencun in March 2024, Pectra in May 2025 and Fusaka in December 2025. The Hoodi delay puts the network’s pace of roughly two major upgrades a year in doubt for 2026. December 15 is a date for testing Glamsterdam, not for activating it on Ethereum mainnet.